INSTALLATION
Assembly
All Assembly, Connections & Installation must be performed by
Competent Personnel Only.
Please note:
In reference to the following instructions, when mentioned, the Left &
Right Hand Platforms and Front & Rear Transverse Beams are viewed
from the drive on perspective.
Proceed with the following:
1. Establish the location of where the hoist will be installed. At this point
ensure the work area is clean and that the concrete is ready for
installation as outlined earlier in
C.1 Foundation
.
2. Place a chalk line across the floor where the front of the hoist will be
positioned.
3. Position the Control Post with the front of the base parallel with the
chalk line.
4. Vertically level the post in both planes. Ensure that the utmost care is
taken with the Control Post until it is safely secured to the concrete.
5. Drill the 4 x 16mm holes of the control post into the concrete and fix the
column with 4 x 16mm x 140mm Tru-Bolts. Ensure the bolts are now
tightened.
6. Now that the Control Post is in position, a qualified electrician can now
connect the electrical wiring to the control box.
7. The platforms and transverse beams need to be assembled into
position. Due to the control post already being bolted into place, it is
important that the hoist is built from that point.
8. Using 200mm high suitable blocks of timber, locate the transverse
beams into position on the timber, noting that there is a front & rear
beam. The difference being that the front beam has a safety striker
attached for the limit switch, this end must be assembled to the control
post position of the hoist.
9. Position the platforms taking note to feed the wire cables through the
transverse beams before bolting the platforms to the beams. To do
this, remove each pulley from the transverse beam, feed the cable
through and replace the pulley. Ensure that the cables are fed through
correctly and that they are positioned on the correct pulley. For the
correct wire cable layout
Refer Section G.1 Wire Cable Diagram.
Please note, there is a Left & Right Platform. The Left Hand Platform
has an outlet on the Front Left for the hydraulic hoses; this must be
positioned closest to the control post.
10. Bolt the front transverse beam into position.
12
Содержание AutoLift AL-6000A
Страница 10: ...Dimensions AL 6000S2 9 ...
Страница 18: ...Parts List 17 ...
Страница 19: ...18 ...
Страница 25: ...Air Line Diagram 24 ...
Страница 26: ...Electric motor jumper pins 25 ...
Страница 27: ...26 ...
Страница 28: ...How to operate Jack 27 ...