Chapter 5
Equipment Power-On and
Power-Off
Table of Contents
Check Before Power-On.............................................................................................5-1
Equipment Power-On .................................................................................................5-4
Check After Equipment Power-On..............................................................................5-4
Equipment Power-Off .................................................................................................5-4
5.1 Check Before Power-On
5.1.1 Checking Equipment Installation
To avoid system fault or failure caused by installation mistake, it is necessary to check the
equipment installation before powering on the equipment.
Caution!
The switches of all power distribution boards and shelves should be OFF during equipment
installation check.
Check equipment installation by the items described in
Table 5-1
.
Table 5-1 Equipment Installation Check List
No.
Check Items
Checking Method
1
Whether the equipment positioning meets the dimension requirements
on the design drawing
The check is based on the
engineering design document
2
Whether the expansion bolt used to fix the cabinet or base (bracket) to
the ground is securely installed;
Whether there exist flat washer and spring washer;
Whether the spring washer is on the flat washer
On-site check
5-1
SJ-20110901170352-005|2011-10-15 (R2.0)