SECTION 6 – COMMISSIONING
PREPARATION – POWER ON
Perform the commissioning using the de-
tailed checks outlined in the EQUIPMENT
PRE-STARTUP & STARTUP CHECK
LIST as the commissioning procedure is
carried out.
Apply power to the unit. Turn ON the option panel
circuit breaker if supplied.
The machine is now live!
Switch Settings
Assure the condensing unit OFF/ON UNIT switch at
the bottom of the keypad is OFF. Place the optional
circuit breaker handle on the panel door to ON. The
customer’s disconnection devices can now be set to
ON.
Verify the control panel display is illuminated.
Assure
the system switches under the SYSTEM SWITCHES
Key are in the OFF position.
Compressor Heaters
Verify the compressor heaters are energized. If the
ambient temperature is above 96 °F (36 °C) the com-
pressor heaters must be on for at least 8 hours before
start-up to ensure all refrigerant liquid is driven out of
the compressor and the oil. If the ambient temperature
is below 86 °F (30 °C), allow 24 hours.
Air Flow Switch
Verify an air flow switch is correctly fitted in the cus-
tomer’s ductwork and wired into the control panel cor-
rectly using shielded cable.
The air flow switch should be connected to terminals
13, 50 and 51 of XTBC1 on the panel. (See
).
Summary of Contents for YLUA0248 Series
Page 4: ...JOHNSON CONTROLS 4 FORM 150 73 NM2 ISSUE DATE 09 07 2020 THIS PAGE INTENTIONALLY LEFT BLANK ...
Page 10: ...JOHNSON CONTROLS 10 FORM 150 73 NM2 ISSUE DATE 09 07 2020 THIS PAGE INTENTIONALLY LEFT BLANK ...
Page 14: ...JOHNSON CONTROLS 14 FORM 150 73 NM2 ISSUE DATE 09 07 2020 THIS PAGE INTENTIONALLY LEFT BLANK ...
Page 30: ...JOHNSON CONTROLS 30 FORM 150 73 NM2 ISSUE DATE 09 07 2020 THIS PAGE INTENTIONALLY LEFT BLANK ...
Page 44: ...JOHNSON CONTROLS 44 FORM 150 73 NM2 ISSUE DATE 09 07 2020 THIS PAGE INTENTIONALLY LEFT BLANK ...
Page 55: ...JOHNSON CONTROLS 55 SECTION 5 TECHNICAL DATA FORM 150 73 NM2 ISSUE DATE 09 07 2020 5 5 ...
Page 57: ...JOHNSON CONTROLS 57 SECTION 5 TECHNICAL DATA FORM 150 73 NM2 ISSUE DATE 09 07 2020 5 5 ...
Page 59: ...JOHNSON CONTROLS 59 SECTION 5 TECHNICAL DATA FORM 150 73 NM2 ISSUE DATE 09 07 2020 5 5 ...
Page 61: ...JOHNSON CONTROLS 61 SECTION 5 TECHNICAL DATA FORM 150 73 NM2 ISSUE DATE 09 07 2020 5 5 ...
Page 63: ...JOHNSON CONTROLS 63 SECTION 5 TECHNICAL DATA FORM 150 73 NM2 ISSUE DATE 09 07 2020 5 5 ...
Page 67: ...JOHNSON CONTROLS 67 SECTION 5 TECHNICAL DATA FORM 150 73 NM2 ISSUE DATE 09 07 2020 5 5 ...
Page 73: ...JOHNSON CONTROLS 73 SECTION 5 TECHNICAL DATA FORM 150 73 NM2 ISSUE DATE 09 07 2020 5 5 ...
Page 77: ...JOHNSON CONTROLS 77 SECTION 5 TECHNICAL DATA FORM 150 73 NM2 ISSUE DATE 09 07 2020 5 5 ...
Page 94: ...JOHNSON CONTROLS 94 FORM 150 73 NM2 ISSUE DATE 09 07 2020 THIS PAGE INTENTIONALLY LEFT BLANK ...
Page 124: ...JOHNSON CONTROLS 124 FORM 150 73 NM2 ISSUE DATE 09 07 2020 THIS PAGE INTENTIONALLY LEFT BLANK ...