HANDLING AND STORAGE
DELIVERY AND STORAGE
To ensure consistent quality and maximum reliability, all
units are tested and inspected before leaving the fac-
tory. Units are shipped completely assembled and con-
taining refrigerant under pressure. Units are shipped
without export crating unless this has been specified on
the Sales Order.
If the unit is to be put into storage, prior to installation,
the following precautions should be observed:
Ensure that all openings, such as water connections,
are securely capped.
Do not store where exposed to ambient air tempera-
tures exceeding 43ºC (110ºF).
The condensers should be covered to protect the fins
from potential damage and corrosion, particularly where
building work is in progress.
The unit should be stored in a location where there is
minimal activity in order to limit the risk of accidental
physical damage.
To prevent inadvertent operation of the pressure relief
devices the unit must not be steam cleaned.
It is recommended that the control panel keys are re-
moved and deposited with a responsible person on-site.
It is recommended that the unit is periodically inspected
during storage.
INSPECTION
Remove any transit packing and inspect the unit to en-
sure that all components have been delivered and that
no damage has occurred during transit. If any damage
is evident, it should be noted on the carrier's freight bill
and a claim entered in accordance with the instructions
given on the advice note.
Major damage must be reported immediately to your
local YORK representative.
MOVING THE CHILLER
Prior to moving the unit, ensure that the installation site is
suitable for installing the unit and is capable of supporting
the weight of the unit and all associated services.
The units are designed to be lifted using cables. A
spreader bar or frame 2250 mm (88") wide should be
used in order to prevent damage to the unit from the
lifting chains (See Figure 3).
CORRECT!
WRONG!
LD03515
FIG. 4 – LIFTING LUGS
Units are provided with lifting eyes extending from the
sides of the base frame which can be attached to di-
rectly using shackles or safety hooks (See Figure 4).
88" (2250 mm)
CORRECT!
WRONG!
LD03514
✓
✓
✓
✓
✓
✗
✗
✗
✗
✗
FIG. 3 – UNIT RIGGING
The unit must only be lifted by the base frame at
the points provided. Never move the unit on roll-
ers, or lift the unit using a fork-lift truck.
Care should be taken to avoid damaging the condenser
cooling fins when moving the unit.
Lifting Weights
For details of weights and weight distribution refer to
the Technical Data Section.
Handling & Storage
Summary of Contents for MILLENNIUM YCAS
Page 53: ...53 YORK INTERNATIONAL FORM 201 18 NM2 WIRING DIAGRAM ACROSS THE LINE START 7...
Page 54: ...54 YORK INTERNATIONAL FIG 12 CONTINUED ELEMENTARY DIAGRAM Technical Data...
Page 59: ...59 YORK INTERNATIONAL FORM 201 18 NM2 WIRING DIAGRAM WYE DELTA START LD03229 FIG 15 CONT D 7...
Page 60: ...60 YORK INTERNATIONAL FIG 15 CONTINUED ELEMENTARY DIAGRAM Technical Data...
Page 62: ...62 YORK INTERNATIONAL FIG 16 POWER PANEL FRONT INSIDE VIEW WYE DELTA START Technical Data...
Page 68: ...68 YORK INTERNATIONAL FIG 24 DETAIL B Technical Data...