XO FLOW – Installation instructions
6
1
INTRODUCTION
Please read these installation instructions carefully before you start installing XO FLOW.
For further details concerning:
•
how the unit is operated
•
how the unit is configured
•
infection control procedures
•
maintenance
•
lists of accessories, detachable parts and consumables
•
legal information
see “Instructions for use, XO FLOW”.
XO FLOW unit must be installed by authorized service personnel.
No unauthorized modification of this equipment is allowed!
2
REQUIREMENTS
2.1
Dimensions of operatory
The unit is intended to be permanently installed in a dental operatory equal to or larger than the
dimensions listed in Figure 1.
The ceiling height of the room should preferably be 255 cm or more for easy
installation of operating light arm – minimum height is 230 cm!
2.2
Floor
Please make sure that the floor construction is designed to carry the weight of the unit and withstand
the forces generated.
The load-bearing capacity of the floor must be > 500 kg/m².
The floor must have a tensile strength to accommodate a force on the four mounting bolts
of > 8kN – see sections 5.2.1 and 5.2.2.