3
075-00
60706-208
INITIAL START UP
******************
***** WARNING *****
******************
DO NOT jump start these generator sets. Starting
these units on a low battery by jump starting them
will cause damage to the engine control module.
Use the following checklist to verify correct in-
stallaion before starting the engine:
�
Engine oil. Check level & fill as required with
proper grade/quantity. Refer to engine owners
manual for proper levels and types.
�
Unit mounting base properly bolted down.
�
Clearance for service and maintenance on all
sides.
�
Proper fuel line material and size.
�
All fuel line connections tight.
�
Fuel line protected and a moisture trap in
stalled (may be required for NG).
�
LP/NG pressure OK. 4-6 oz. (7- in. WC).
�
Battery connections clean and tight.
�
Battery fully charged.
�
All AC and DC wiring installed and properly
protected.
After completing the above checklist, the generator
set is ready for the initial start-up test.
START UP PROCEDURE
Engine Generator Set only
Move the left hand toggle switch from OFF to the
ON position. The alarm light should go out. Next
move the right hand toggle witch from the AUTO to
the RUN position. You should hear the fuel solenoid
engage at this time. Next lift the toggle switch to the
START position and hold. The engine starter should
engage and the engine will start. As soon as the en-
gine starts release the toggle switch and it will return
to the run position. If the engine does not start after
5 seconds release the switch and let the starter rest
for 5 seconds and re-attempt to start. If the unit still
will not start, consult the troubleshooting guide in the
back of this manual.
WIRE #
PURPOSE
RECOMMEND
COLOR
# 5
Battery Positive
Black
# 1
Battery Negative
White
# 24
Fuel Solenoid
Red
# 22
Start
Orange
These wire colors are a recommendation only. The
wires terminate on TB7 as follows:
WIRE #
COLOR
TB7 TERMINAL
# 5
Black
# 3
# 1
White
# 2
# 24
Red
# 4
# 22
Orange
# 7
Jumpers will need to be installed as follows:
WIRE #
COLOR
TB7 TERMINAL
# 5
Black
# 3 & # 5
# 5
Black
# 5 & # 8
The following is an optional way to interconnect the
Generator and the Transfer Switch. the wires termi-
nate on TB7 terminal as follows:
WIRE #
COLOR
TB7 TERMINAL
# 1
White
# 2
# 24
Red
# 4
# 22
Orange
# 7
The following leads are wire-nutted together:
WIRE #
COLOR
FROM
# 5
Black
Generator
# 5
Black
TB7 # 3
# 5
Black
TB7 # 5
#5
Black
TB7 # 8
Summary of Contents for ULPSS12H4W/E
Page 1: ...11075 00 60706 208 INSTALLATION AND OPERATORS MANUAL PACKAGED STANDBY SYSTEM ULPSS12H4W E...
Page 10: ...11075 00 10 60706 208...
Page 18: ...11075 00 18 60706 208 AC AND DC GENERATOR SCHEMATIC...
Page 20: ...11075 00 20 60706 208 ENGINE GENERATOR SET LAYOUT ULPSS12H4W E...
Page 21: ...21 11075 00 60706 208 ENGINE GENERATOR SET PAD LAYOUT...
Page 23: ...23 11075 00 60706 208 DATE HOURS ITEM WORK PERFORMED MAINTENANCE LOG...