ATTENTION
The stack configuration shall be concluded by interlocking the modules by using the module feet as shown below
GENERAL PREPARATION
Before Installation
Ensure that all the modules are turned OFF
Battery installation location should be at least 20m away from sources of heat, sparks or other sources of extreme temperature.
Battery connecting cables should be as short as possible to prevent excessive voltage drops..
Batteries with different capacity, different type/model or design or from different manufacturers cannot be connected together.
1. Before connecting the battery, the battery positive and negative poles need to be carefully checked to
ensure correct installation.
2. The installation location must be on a flat ground, in a dry clean and protected room, away from water
and humidity.
1) Original Position of the feet
2) Loose both screws and
remove the feet
3) Install and secure the feet across two
modules by using the original screws