70
For balanced flue systems tested
together with the wall mounted gas fired
boiler, the requirement for a tightness
test during commissioning by the flue
gas inspector is not applicable.
We recommend that your heating engi-
neer carries out a simple leak/tightness
test during the commissioning of your
system. For this, it would be sufficient to
check the CO
2
or O
2
concentration in the
combustion air at the annular gap of the
balanced flue pipe.
The flue pipe is deemed to be gas-tight
if the CO
2
concentration in the combus-
tion air is no higher than 0.2 % or the
O
2
concentration is at least 20.6 %.
If actual CO
2
values are higher or O
2
val-
ues are lower, then pressure test the flue
pipe with a static pressure of 200 Pa.
Auxiliary burner removal
B
C
D
E
A
Commissioning, inspection, maintenance
Further details regarding the individual steps
(cont.)
5618 294 GB
Summary of Contents for C3HA
Page 39: ...39 2 2x 1 Installation sequence Removing the front panel 5618 294 GB Installation ...
Page 42: ...42 1 2 Installation sequence Removing the transport brackets 5618 294 GB ...
Page 151: ...151 Checking and replacing resistors B C A Troubleshooting Repairs cont 5618 294 GB Service ...
Page 181: ...181 Parts lists Control unit assembly cont 5618 294 GB Service ...
Page 183: ...183 Parts lists Miscellaneous assembly cont 5618 294 GB Service ...
Page 191: ...191 5618 294 GB ...