40
Aligning the boiler
1.
Align the Vitotwin 300-W vertically
and horizontally in all three axes.
Note
Take any additional measures
required on site.
2.
Place the supplied circular level on
the Stirling engine plate and check
levels.
The circular level is packed sepa-
rately with the gas restrictors.
The inclination along all axes must be
≤
1°: bubble no more than halfway out
of the marked area.
3.
If necessary, alter the position by
adjusting the rubber dampers on the
rear boiler panel and the wall mount-
ing bracket.
Installation sequence
Removing the front panel
(cont.)
5618 294 GB
Summary of Contents for C3HA
Page 39: ...39 2 2x 1 Installation sequence Removing the front panel 5618 294 GB Installation ...
Page 42: ...42 1 2 Installation sequence Removing the transport brackets 5618 294 GB ...
Page 151: ...151 Checking and replacing resistors B C A Troubleshooting Repairs cont 5618 294 GB Service ...
Page 181: ...181 Parts lists Control unit assembly cont 5618 294 GB Service ...
Page 183: ...183 Parts lists Miscellaneous assembly cont 5618 294 GB Service ...
Page 191: ...191 5618 294 GB ...