110
If the system is to be filled independently of the com-
missioning assistant, the diverter valve can be moved
to the central position via the filling function (see "Fill-
ing the heating system"). In this position, the control
unit can be switched off and the system can be filled
completely.
When the function is enabled, the burner shuts down.
The program automatically becomes inactive after
20 min.
Screed drying
When activating screed drying, observe the informa-
tion provided by the screed manufacturer.
When screed drying is activated, the heating circuit
pump for the heating circuit with mixer starts and the
flow temperature is maintained in accordance with the
selected profile. On completion (30 days), the heating
circuit with mixer is controlled automatically according
to the set parameters.
Note
Temperature profile 6 ends after 21 days
Observe EN 1264. The report to be provided by the
heating contractor must contain the following details
regarding heat-up:
■
Heat-up data with respective flow temperatures
■
Max. flow temperature achieved
■
Operating state and outside temperature during
handover
Different temperature profiles can be set via parameter
F1 in the
"Heating circuit"
group.
The function continues after a power failure or after the
control unit has been switched off. "Heating and DHW"
is started when screed drying is finished or if parame-
ter F1:0 is set manually.
Temperature profile 1: (EN 1264-4) parameter F1:1
Flow temperature
°C
1
5
10
15
20
25
30
Days
50
40
30
20
10
Fig. 70
Temperature profile 2: (ZV parquet and floor technology) parameter F1:2
Flow temperature
°C
Days
50
40
30
20
10
1
5
10
15
20
25
30
Fig. 71
Temperature profile 3: Parameter F1:3
Flow temperature
°C
Days
50
40
30
20
10
1
5
10
15
20
25
30
Fig. 72
Function description
Control functions
(cont.)
5778741