Chapter 3 Installing CPRIAdvisor CAP-100 and CAE-100
22
CPRIAdvisor Installation Guide
NOTE
The number of optical cables to be connected varies based on your installation
environment.
8
Turn the
POWER
switch on.
9
Check whether the status LED changes from red to green and wait until the green LED
illuminated.
10
Connect the uplink interface port of the coupler to the CPRIAdvisor CAM-100.
NOTE
Once the installation of the CAP-100 is complete, you need to set IP address, date and
time via Serial before connecting to CAM.
Installing the CPRIAdvisor CAE-100
After inspecting your shipment, follow the procedure below to install the CPRIAdvisor CAE-100.
Procedure
To install with a 19-inch rack:
1