We remove the boiler shell.
−
Break out an opening in the left side shell.
−
We remove the grate and pull out the burner with mixer from the basement (the connection accessories
are as follows: 6 pc screw M10 x 30, 12 pc washer 10,5, 6 pc nut M10).
−
We unscrew the blind flange from the basement left-hand side and screw it to the right-hand side (the
connection accessories are as follows: 4 pc screw M10 x 30, 8 pc washer 10,5, 4 pc nut M10). The blind
flange with basement connection must be sealed with mastic.
Fig. no. 17
Boiler conversion from the right-hand to left-hand design – dismantling of burner and
blind flange
−
We apply mastic to the burner with mixer flange and we put the burner into the basement from the left-
hand side and screw it (the connection accessories are as follows: 6 pc screw M10 x 30, 12 pc washer
10,5, 6 pc nut M10).
−
We remove the old mastic from the grate. We apply a reasonable quantity of new mastic to the bearing
surfaces and we mount the grate in the burner. (Note: In front view to boiler the grate trimming must
always be to the rear wall).
1.
The boiler without feeder, fuel
reservoir and shells
2.
Grate
3.
Burner
4.
Washer 10,5
5.
Nut M10
6.
Screw M10 x 30
7.
Blind flange