Vertiv™ NetSure™ HVT F02 CK1 Power System User Manual
22
Figure 1.22
Installing a Rectifier
Rectifier
Captive Screw
Latch Release
Front View
Unlock Position
Lock Position
6. Repeat the above steps for each rectifier being installed in the system.
7. For some temporarily unused rectifiers in the system, reinstall the removed blank panels in these locations.
8. After the rectifiers are physically installed in the module mounting shelf(s), they are ready for operation immediately after
power is supplied to them.
9. After the rectifier is powered on, observe the status of the indicators on the front panel. If the rectifier is running normally, see
Table 1.12 for the status of the indicators.
Table 1.12
Status and indicators
Indicator
Normal state
Indicator
Normal state
Power indicator (green)
On
Alarm indicator (red)
Off
Protection indicator (yellow)
Off
1.7
Installation Checklist
After installation, security check should be conducted using the following checklist in Table 1.13.
Table 1.13
Installation checklist
No
Standards And Requirements
Pass
Notes
1
Constructed according to the design plan
Yes/No
2
The system cabinets are fixed with expansive screws
Yes/No
3
The cabinets are aligned
Yes/No
4
The installation equipment is clean
Yes/No
5
The installation equipment facilitates wiring
Yes/No