![Vertiv NetSure HVT F02 CK1 User Manual Download Page 12](http://html1.mh-extra.com/html/vertiv/netsure-hvt-f02-ck1/netsure-hvt-f02-ck1_user-manual_1008116012.webp)
Vertiv™ NetSure™ HVT F02 CK1 Power System User Manual
4
NOTE!
If the user does not use the layout mode in Figure 1, then parallel copper bars and parallel cables should be
customized. When placing an order, please provide the cabinet’s layout mode of the power system.
The power system adopts centralized-distributed control method, DC distribution cabinets can be placed separately from the
system. Typical applications are in different load concentration, such as different floors, nearby for power distribution. When DC
distribution cabinets are placed separately from the rectifier cabinet of the system, use cables to parallel connect DC distribution
cabinets.
1.3.2
Installing Side Doors
After determining the cabinet layout mode, check side doors installation of the rectifier cabinets, DC distribution cabinets and AC
distribution cabinets. Meet the following requirements before being installed:
1. Confirm that both ends of the whole row of cabinets have side doors for sealing.
2. Confirm that side doors are not installed in the middle of the rectifier cabinet and DC distribution cabinet, to facilitate system
inside parallel and internal wiring.
If the side doors installation of the rectifier cabinet, AC distribution cabinet and DC distribution cabinet does not meet the above
requirements, adjust the layout at site. The side doors are for the general design, which can be adjusted between each cabinet
according to the actual situations. See Figure 1.2 for side doors installation.
Figure 1.2
Installation of side doors
1.3.3
Installing Power Cabinet
The power cabinet can be installed directly onto a bracket or cement floor.
Determine the cabinet installation position in machine room according to Figure 1.3.
Figure 1.3
Determining cabinet installation position