It is recommended that only ELGA LabWater service personnel or
other fully trained staff should perform the procedure for sanitization of
the unit and docking vessel/reservoir.
8.2 Tablet sanitization
8.2.1
Standard Sanitization
The unit is sanitized to reduce the growth of microbiological
contamination within the unit. The
MEDICA-D 7/15 US
has a built-in
sanitization port, which allows the sterilant to be introduced into the
water feeding the RO. Please read this entire section to become
familiar with the procedure before you start.
The sanitization frequency required is dependent on the feedwater,
local environment, usage patterns and application. As a general rule,
ELGA LabWater recommends sanitization of the RO at 6 monthly
intervals. However, the period between sanitizations could be
extended in particular circumstances. For example, microbial growth
will usually be lower with clean feed water, well-maintained pre-
treatment, low temperatures and heavy usage.
WARNING! ALWAYS WEAR RUBBER GLOVES, APRON AND
FACEMASK. DO NOT BREATHE FUMES OR ALLOW
TO COME IN CONTACT WITH SKIN OR EYES.
ALWAYS FOLLOW RECOMMENDATIONS FOUND IN
THE MANUFACTURERS MATERIAL SAFETY DATA
SHEET AND ANY APPLICABLE OSHA STANDARDS
FOR THE CHEMICAL BEING USED.
WARNING! LABEL
THE
MACHINE
WITH
APPROPRIATE
WARNING SIGNS SUCH A
S “DO NOT USE/
CONTAINS STERILANT” (NOT PROVIDED)
EfferSan
™ is a multi-purpose disinfecting tablet.
Refer to the EfferSan
™ label for additional information and follow all
applicable directions for use on the manufacturer’s label in conjunction
with the following instructions.
Step 1 - Start Sanitization Cycle
1. ENSURE that the docking vessel/reservoir level
indication on the graphics display is showing
>10%. If display shows >40%, >70% or 100%,
dispense water until display changes to >10%.
2. PRESS the PROCESS button to stop the
process.
3. TURN OFF the electrical supply.
4. WAIT one minute for residual pressure to
dissipate.
5. ISOLATE the pump feed line from the reservoir
by closing valve V3 (see page 15) then
disconnect the tube from the unit side of the valve
(V3). Direct the line to drain.