COMMISSIONING
61
Shorter lengths
We manufacture shorter lengths at our factory according to your specifications. If shorter lengths still need to
be adapted on site, modify the conductor system as follows.
NOTICE!
►
The left side of the conductor rails has been widened at the factory to prevent it from moving inside the
plastic housing. Therefore always only shorten the right side. (1) indicates the WCS mount.
Step 1
Required tools:
⚒
Contact angle
Assembly steps:
1. Push in the conductor rail on the right side using
a wooden board until they are flush with the insu-
lation housing.
2. Mark the new section length at right angles.
Step 2
Required tools:
⚒
Hack saw
Assembly steps:
1. Saw off the conductor rail at the marking.
Step 3
Required tools:
⚒
Tape measure
⚒
File
Assembly steps:
1. Push the conductor rail back until the same pro-
jection "B" of 34?mm is achieved on both sides.
2. Deburr the shortened conductor rail ends and
the insulation profile.
Bending the conductor system
The conductor rails are only bent at the factory.
Them minimum radius is:
Inner radius R = 1000 mm
Outer curves R = 1500 mm.
Summary of Contents for VKS10
Page 89: ...MAINTENANCE 87 Connecting caps mast assembly before Connecting caps mast assembly after ...
Page 96: ...PROTECTIVE MEASURES 94 10 PROTECTIVE MEASURES 10 1 EU conformity declaration ...
Page 99: ...CE Technical Documentation DQS certified in accordance DIN EN ISO 9001 2015 OHSAS 18001 2007 ...