Chapter 3: Configuration and commissioning
SynaG Series Installation Manual
61
Battery startup
To power up the control panel from the batteries, press the battery start button on
the control panel PCB (marked as BAT. START, see Figure 20 below). Keep the
button pressed for approximately 5 seconds.
Figure 20: Battery startup button
Functional tests
Create a short and open circuit in the zone to test fault reporting for each.
Activate a manual call point to test manual alarm reporting. The control panel
should override any configured delays and activate alarm notification devices and
fire routing (where applicable) immediately.
Activate a detector to test automatic alarm reporting. The control panel should
initiate any configured delays and activate alarm notification devices and fire
routing (where applicable) once the delay time has elapsed.
Using a multimeter, verify that the fault relay is activated when a fault is reported
and that the alarm relay is activated when an alarm is reported.
Response times
Response times for standard events are as follows.
Table 28: Response times for standard events
Event Response
time
Alarm
Less than 3 seconds
Zone fault
Less than 30 seconds
Sounder fault
Less than 30 seconds
Fire routing fault
Less than 30 seconds
Expansion board fault
Less than 100 seconds
Summary of Contents for Kidde AirSense SynaG Series
Page 1: ...SynaG Series Installation Manual P N 501 435003 1 10 REV 1 0 ISS 14OCT11 ...
Page 6: ...iv SynaG Series Installation Manual ...
Page 10: ...Chapter 1 Introduction 4 SynaG Series Installation Manual ...
Page 72: ...Chapter 4 Maintenance 66 SynaG Series Installation Manual ...
Page 84: ...Chapter 5 Technical specifications 78 SynaG Series Installation Manual ...
Page 96: ...Appendix A Configuration presets 90 SynaG Series Installation Manual ...
Page 100: ...Appendix B Product compliance 94 SynaG Series Installation Manual ...
Page 103: ......
Page 104: ......