3.2. Device placement and Considerations
The device shouldn’t be unpackaged until it reaches to the installation spot so that no damage emerges.
It is also crucial that where the device will be placed be chosen carefully. Ground should have the nature
to bear weight of the device and dynamic loads to arise during operation of the device.
Necessary lightening should have been provided at the environment where the device is placed so that
maintenance works could be carried out with ease.
There should be left extra spaces at the width to let for maintenance works at the area where the device will
be placed. Spaces to be needed for placement according to device models are seen below.
Size\ Model
URTP055
URTP070
URTP090
URTP110
URTP140
URTP180
URTP230
A [mm]
1200
1200
1600
1600
1850
1850
2400
B [mm]
900
900
1100
1100
1350
1350
1500
C [mm]
900
900
1100
1100
1350
1350
1500
D [mm]
900
900
1100
1100
1350
1350
1500
If there are higher walls than the device’s height near
where the device will be placed and if condenser side of
the device faces this wall, the line between upper surface
of the device and upper surface of walls should be 60
degrees at maximum. At higher degrees, the device won’t
have the necessary air flow.
If the device cannot be taken away from walls, the linage
to the device’s condenser should be hollowed out and air
flow should be provided.
If the distance between wall and the device more than