The equipment is prepared so that the installer simply has to connect the input
of panels, grid, loads and batteries, if applicable, to the place indicated below.
All protections specified in the schematic are included and pre-assembled, thus
facilitating the function of the installer.
•
Photovoltaic panels must be connected in series to the input specified
below. Internally connects to its corresponding fuses.
•
The inverter's grid output is protected with its differential and automatic
switches. It must be connected after the magnetothermal of the general
housing frame and to the specified internal terminals of the SunBox by a 6
mm
2
hose.
•
The CT-meter comes pre-assembled and connected inside the SunBox.
•
In case batteries need to be installed, the SunBox Series 5.0 comes ready
to store up to 2 Turbo Energy Lithium Series 48V 5.1kWh batteries. Its
installation is explained below.
*The Grid and Load outputs in normal grid operation will be the same as they are
internally connected, however, in case of grid failure, if the system stays running
in off-grid, the inverter opens the contact that joins the grid and load and leaves
the load output running in off-grid. This is because the inverter cannot operate in
island mode, therefore the automatic must be separated from the frame so that
it can operate in off-grid. The operation in off-grid will depend on whether the
corresponding batteries have been installed and will operate by solar energy
and batteries only for the duration of renewable energy. It should be noted that
the power will be limited to 5 kW, therefore it is not possible to include loads that
require a lot of power.