TL60ECV
-
Section 3: Setup 3-3
Pre-Operating Inspection
Before wrapping at a new site:
•
Check oil tank level. Leave about 1/4” from top of sight guage when filling to avoid overflow.
• Check gas tank level.
• Check Tire Pressure.
• Complete a walk around inspection.
•
Check engine for hazardous flammable material buildup.
• Check guarding is secure.
Manual Mode Test Run
Test machine in Manual wrap mode without bales and without plastic film rolls installed.
1. Start engine, refer to
Balewrapper Starting
,
2. Turn on control panel, refer to
.
3. Advance bale ram towards hoop chamber by turning FWD-REV control panel switch to
REV
.
4. While holding bale ram switch in
REV
, engage Hoop Rotate button to test hoop rotation speed.
5. Release REV bale ram switch and Hoop Rotate when bale ram reaches fully extended position.
6. Return the bale ram to front of bale wrapper (“Home” position) by turning
FWD-REV
bale ram
switch to
FWD
(forward).
Auto Mode Test Run
Test machine in Auto mode without bales and without plastic film rolls installed.
1. Switch control screen to auto mode, refer to
2. Press the bale trigger using a pole inserted between the bale ram and the bale deck.
DANGER: DO NOT
attempt to engage the bale trigger by hand.
3. The TL60ECV balewrapper should automatically follow the sequence of the manual wrap mode
without the manual operation of the control screen.
Wrapping Site
• Select a site that will allow room to make an adequate bale row length.
•
Site should be free of grass and debris which can attract rodents that damage plastic film.
• There should be space for at least 50 bales in a row.
•
Select a site that is accessible in winter conditions and does not flood in the spring.
• Avoid soft ground, as the wrapper will not move forward smoothly if it is sinking into the ground.
• Operate on level ground or a slight uphill grade for best bale row compaction.
Summary of Contents for TL60ECV
Page 7: ...Intentionally Left Blank...
Page 12: ...TL60ECV Section 2 Safety 2 3 Clearance Markers Part No DEAMBER Part No DERED...
Page 13: ...2 4 Section 2 Safety TL60ECV Safety Decal Locations NOTE Decals shown are not to scale...
Page 39: ...11 1 Section 11 Diagnostics TL60ECV Section 11 Diagnostics Manifold Solenoid Functions...
Page 59: ...VII Imperial Torque Value Chart TL60ECV Imperial Torque Value Chart...
Page 60: ...TL60ECV Metric Torque Value Chart VIII Metric Torque Value Chart...