7
Commissioning
7.1 Initial commissioning
Personnel:
Skilled qualified electrician
Before initial commissioning:
Remove protective film, if any.
Ensure that the unit is clean. If necessary, clean the
casing and the inlet and outlet openings from dust.
Professional electrical connections:
–
Check and ensure that the actual supply voltage
is the same as the one given on the rating plate.
–
Ensure that the ventilation unit has been cor-
rectly earthed.
Ensure that all heat exchangers are clean and free
from residues and foreign matter.
Check filters for correct fit and contamination
9.2.1 ‘Checking and replacing the filters’
. Should the filters have been contami-
nated even before installation, replace them.
For commissioning see also VDI 6022, part 1 – 'Hy-
giene requirements for ventilation and air-conditioning
systems and units'.
1.
Switch on the power supply.
ð
The ventilation unit is on.
2.
Configure the control of the ventilation unit, if nec-
essary.
7.2 Control of the ventilation unit
Control of ventilation units
For units with TROX FSL
‑
CONTROL III control system
Ä
Installation and configuration manual, FSL
‑
CON-
TROL III single room control system.
For units without integral controls from TROX follow the
instructions of the controls provider.
7.3 X-TAIRMINAL
TROX X-TAIRMINAL is a project-specific software for
visualisation, operation and monitoring of ventilation
systems on a panel PC. The presentation is done on
several levels that contain different information. The dif-
ferent menu levels are selected by pressing the respec-
tive objects displayed.
Overview
The
‘Overview’
page represents the overall ventila-
tion system, which can consist of various sub-ventila-
tion systems. For example, classrooms can be venti-
lated with decentralised SCHOOLAIR ventilation units,
whereas the cafeteria or sports hall are ventilated with
central X-CUBE ventilation units.
On the
‘Overview’
page, the operating mode and
pending alarm messages for each system can be
recorded at a glance.
①
②
③
④
SCHOOLAIR
X-AIRCONTROL
Fig. 43: System overview
j
Menu
k
Navigation bar
l
Spatial representation
m
Status line
SCHOOLAIR
In the
‘SCHOOLAIR’
room overview, the overview of
the decentrally ventilated rooms is displayed.
The operating mode can be set here or the remaining
filter time can be reset after a filter change.
In addition, the following information is shown for the
individual rooms:
Operating mode
Operating mode
Source of the operating mode
Consolidated alarm, Category A
Consolidated alarm, Category B
Commissioning
X-TAIRMINAL
Decentralised ventilation units SCHOOLAIR-S-HV
31