Revision E November 2020
Foundation/Anchoring
Warning:
Ensure that this assembly conforms with the guidance provided by the
AASHTO Roadside Design Guide, including, but not limited to, those regarding
placement on or adjacent to curbs.
Asphalt Installations
REACT 350
®
II
systems with a Self-Contained Backup may be installed in construction zones on
asphalt. Assemblies on
Asphalt Concrete
(“A.C.”)
must provide a minimum 3” [76 mm] layer of
asphalt over a minimum 3” [76 mm] layer of
Portland Cement Concrete
(“P.C.C.”)
, 6” [152 mm]
layer of asphalt over 6” [152 mm] layer of subbase, or 8” [203 mm] layer of asphalt with no
subbase.
Important:
Only 18” [460 mm] threaded rods,
utilizing Trinity Highway approved
adhesive, can be used with asphalt foundations. Contact Customer Service for a
complete list of approved adhesives (p. 3).
Concrete Installations
For concrete installations, the
REACT 350
®
II
should be installed only on an existing or freshly
placed and cured concrete base (28 MPa [4000 psi] minimum). Orientation of the concrete base
and the attenuator must comply with the project plans or as otherwise determined by the resident
project engineer or appropriate highway authority.
Recommended dimension and reinforcement specifications for new concrete pads can be found
in your site specific drawing package or standard drawings in the back.
The
REACT 350
®
II
may be installed on any of the following foundations using the specified
anchorage:
Foundation A: Concrete Pad or Roadway
Foundation: 8” [200 mm] minimum depth P.C.C.
Anchorage:
Approved adhesive
with 7 1/2” [190 mm] studs 6” [152 mm] embedment
Foundation B: Asphalt over P.C.C.
Foundation: 3” [76 mm] minimum A.C. over 3” [76 mm] minimum P.C.C.
Anchorage:
Length of anchor required is 18” [460 mm] 16 1/2” [420 mm] embedment
Foundation C: Asphalt over Compacted Subbase (“C.S.”)
Foundation: 6" [150 mm] minimum A.C. over 6" [150 mm] minimum C.S.
Anchorage:
Approved adhesive with
18" [
460
mm] studs 16 1/2” [420 mm] embedment
Foundation D: Asphalt
Foundation: 8” [200 mm] minimum A.C.
Anchorage:
Approved adhesive with
18" [
460
mm] studs - 16 1/2” [420 mm] embedment
Summary of Contents for REACT 350 II
Page 1: ......
Page 39: ...TrinityHighway com 38 Revision E November 2020 REACT 350 II TL 3 w Concrete Backup R626C036U...
Page 40: ...TrinityHighway com 39 Revision E November 2020 Transition Assembly SC BU UNI 117815...
Page 41: ...TrinityHighway com 40 Revision E November 2020 Transition Assembly SC BU N 616120...
Page 42: ...TrinityHighway com 41 Revision E November 2020 Transition Assembly SC BU N w Rub Rail 117827...
Page 43: ...TrinityHighway com 42 Revision E November 2020...
Page 44: ...TrinityHighway com 43 Revision E November 2020...
Page 45: ...TrinityHighway com 44 Revision E November 2020 Base Track Assembly 36 Wide Units 605028...
Page 46: ...TrinityHighway com 45 Revision E November 2020...
Page 48: ...TrinityHighway com 47 Revision E November 2020...
Page 49: ...TrinityHighway com 48 Revision E November 2020...
Page 50: ...TrinityHighway com 49 Revision E November 2020 Transition Assembly w Concrete Backup 616084...
Page 52: ...TrinityHighway com 51 Revision E November 2020...
Page 53: ...TrinityHighway com 52 Revision E November 2020...
Page 54: ...TrinityHighway com 53 Revision E November 2020 Nose Cover Assembly TL 3 617967...
Page 55: ...TrinityHighway com 54 Revision E November 2020 Chain CYL Connector Assembly 606182...
Page 56: ...TrinityHighway com 55 Revision E November 2020...
Page 57: ...TrinityHighway com 56 Revision E November 2020 Cable Assemblies 605780...
Page 58: ...TrinityHighway com 57 Revision E November 2020...
Page 59: ...TrinityHighway com 58 Revision E November 2020 Reflector Assembly White Amber Side 613705...
Page 60: ...TrinityHighway com 59 Revision E November 2020 Misc Hardware 611324...
Page 61: ...TrinityHighway com 60 Revision E November 2020 Debris Cover Assembly 36 606715...
Page 62: ...TrinityHighway com 61 Revision E November 2020 Debris Cover Assembly 36 606716...
Page 63: ...TrinityHighway com 62 Revision E November 2020 Debris Cover Assembly 618102...
Page 64: ...TrinityHighway com 63 Revision E November 2020 Drivable Pile Anchor DPA 607938...
Page 65: ...TrinityHighway com 64 Revision E November 2020 Sign Post Assembly 115254...
Page 66: ...TrinityHighway com 65 Revision E November 2020 NOTES...
Page 67: ...TrinityHighway com 66 Revision E November 2020 NOTES...
Page 68: ......