Transport and installation
TNL20
DTE022DE - 24.06.2021
Transporting the machine
Technical requirements – transport rollers
Height
mm
max. 110
Steerable
mm
max. 610 x 520
Capacity:
kg
up to 12000
e.g., transport rollers type F6 and L6, by GKS, for loads up to 12 t
After removing the planks, the machine can also be lowered onto rollers and
transported to its installation site and/or moved into the position required for
installation.
The transport supports necessary for this can be found in the accessories to
the machine.
• Screw the 4 adjusting screws
(1)
in to the same depth and lightly counter
them with hex head lock nuts
(2)
(the adjusting screws can be found in the
accessories in the chip conveyor or the chip pan).
Set the machine down onto the adjusting screws (the transport supports
must fit under the machine for mounting).
The adjusting screws can be found in the accessories in the chip conveyor
or the chip pan.
Summary of Contents for TNL20
Page 6: ...Table of Contents 6 Transport and installation TNL20 DTE022EN 02 08 2022...
Page 10: ...10 Transport and installation TNL20 DTE022EN 14 03 2022 Safety...
Page 20: ...20 Transport and installation TNL20 DTE022EN 14 03 2022 General...
Page 66: ...66 Transport and installation TNL20 DTE022EN 14 03 2022 Electrical connection...
Page 68: ...68 Transport and installation TNL20 DTE022DE 24 06 2021 Operating material...
Page 70: ...70 Transport and installation TNL20 DTE022DE 24 06 2021 Pneumatic connection...
Page 72: ...72 Transport and installation TNL20 DTE022DE 24 06 2021 Switching on the machine...
Page 73: ......