124
⎯
6 F 2 S 0 8 2 8
5. Installation
5.1 Receipt of Relays
When relays are received, carry out the acceptance inspection immediately. In particular, check
for damage during transportation, and if any is found, contact the vendor.
Always store the relays in a clean, dry environment.
5.2 Relay
Mounting
A flush mounting relay is included. Appendix E shows the case outline.
For details of relay withdrawal and insertion, see Section 6.7.3.
5.3 Electrostatic
Discharge
CAUTION
Do not take out the relay unit outside the relay case since electronic components on the modules
are very sensitive to electrostatic discharge. If it is absolutely essential to take the modules out of
the case, do not touch the electronic components and terminals with your bare hands.
Additionally, always put the module in a conductive anti-static bag when storing it.
5.4 Handling
Precautions
A person's normal movements can easily generate electrostatic potentials of several thousand
volts. Discharge of these voltages into semiconductor devices when handling electronic circuits
can cause serious damage. This damage often may not be immediately apparent, but the reliability
of the circuit will have been reduced.
The electronic circuits are completely safe from electrostatic discharge when housed in the case.
Do not expose them to risk of damage by withdrawing the relay unit unnecessarily.
The relay unit incorporates the highest practical protection for its semiconductor devices.
However, if it becomes necessary to withdraw the relay unit, precautions should be taken to
preserve the high reliability and long life for which the equipment has been designed and
manufactured.
CAUTION
•
Before removing the relay unit, ensure that you are at the same electrostatic potential as the
equipment by touching the case.
•
Use the handle to draw out the relay unit. Avoid touching the electronic components,
printed circuit board or connectors.
•
Do not pass the relay unit to another person without first ensuring you are both at the same
electrostatic potential. Shaking hands achieves equipotential.
•
Place the relay unit on an anti-static surface, or on a conducting surface which is at the same
potential as yourself.
•
Do not place the relay unit in polystyrene trays.
Summary of Contents for GRL150-100 Series
Page 149: ... 148 6 F 2 S 0 8 2 8 ...
Page 154: ... 153 6 F 2 S 0 8 2 8 Appendix B Signal List ...
Page 180: ... 179 6 F 2 S 0 8 2 8 Appendix C Binary Output Default Setting List ...
Page 182: ... 181 6 F 2 S 0 8 2 8 Appendix D Details of Relay Menu ...
Page 195: ... 194 6 F 2 S 0 8 2 8 ...
Page 196: ... 195 6 F 2 S 0 8 2 8 Appendix E Case Outline ...
Page 199: ... 198 6 F 2 S 0 8 2 8 ...
Page 200: ... 199 6 F 2 S 0 8 2 8 Appendix F Typical External Connections ...
Page 223: ... 222 6 F 2 S 0 8 2 8 ...
Page 228: ... 227 6 F 2 S 0 8 2 8 Appendix I Return Repair Form ...
Page 232: ... 231 6 F 2 S 0 8 2 8 Appendix J Technical Data ...
Page 238: ... 237 6 F 2 S 0 8 2 8 Appendix K Symbols Used in Scheme Logic ...
Page 241: ... 240 6 F 2 S 0 8 2 8 ...
Page 242: ... 241 6 F 2 S 0 8 2 8 Appendix L Inverse Time Characteristics ...
Page 248: ... 247 6 F 2 S 0 8 2 8 Appendix M IEC60870 5 103 Interoperability ...
Page 260: ... 259 6 F 2 S 0 8 2 8 Appendix N Resistor Box Option ...
Page 263: ... 262 6 F 2 S 0 8 2 8 ...
Page 264: ... 263 6 F 2 S 0 8 2 8 Appendix O Ordering ...
Page 267: ......