Operating manual
Commissioning
TW63B drive
thyssenkrupp Aufzugswerke
53
Version 09/2018
7 Commissioning
7.1 Work steps
For assembly, use only original construction and mounting parts from thyssenkrupp
Aufzugswerke GmbH, as otherwise no warranty can be provided.
Before commissioning the machine, the following points must be checked and carried
out:
OK
Work step
1. Remove safety, auxiliary and installation tools from the
danger zone.
2. Check setup and alignment of machine, base frame, rope
departure and base.
3. Check the oil drain pipe is seated securely and leak-tight.
(Machine is filled with oil at the plant)
4. Check the gear oil level.
5. Check the secure mounting of the machine and base frame.
6. With a side or oblique rope departure, the gear housing is
secured against moving with end stops and set screws.
7. Make sure that the bolts are tightened with the prescribed
torque and secured.
Chapter 10.2
8. Check the brake shoe stroke and setting
Chapter 8.5.2
9. With SA3, SA3.1 and SA15, check the setting and function of
the brake test switches.
Chapter 9.1
10. Conduct a brake test with one brake shoe in each case.
Chapter 8.6
11. Check the function of the handbrake release.
Chapter 10.2
12. Fit the rope guard and set the distance to the traction sheave.
Chapter 6.3
13. Check whether the power connections and earthing of the
motor, forced ventilation and brake magnet are connected
and secured.
14. Stick the direction arrow (Up / Down) clearly visible on the
motor near the handwinding wheel according to the direction
of travel.
Table 7.1-1
Summary of Contents for TW63B
Page 1: ...thyssenkrupp Aufzugswerke Operating manual TW63B drive...
Page 84: ...Part No 9950 000 6021 mit 1024 Imp Part No 9950 000 6021 mit 4096 Imp...
Page 85: ...Part No 00 990 16 03 0 with 1024 pulses...
Page 86: ...Part No 00 990 19 03 0 mit 1024 Imp...
Page 87: ......
Page 103: ...Design for TW63...
Page 104: ......