FWT START~UP REPORT (Con’t)
Electrical System Checks
1.
De-Energized
a. Check for any loose connections
b. Check circuit breaker disconnect mechanisms / Mechanical interlocks operate
properly
c. Check VFD size and rating (voltage and horsepower)
d. Check and set motor start protectors (MSP) for correct size and setting.
e. Ensure all system components are adjusted to proper settings (temperature,
amperage)
2.
Energized
a. Connect proper input voltage power to line side of panel
b. Energize incoming power circuit.
c. Check for proper line voltage.
d. Check voltage between all neutral terminations and panel ground (should be
zero volts)
e. Check internal power supplies for proper voltage output(s) and adjust as required
f. Test and verify proper operations of all GFCI devices
g. Check operation of cabinet cooling fans, adjust thermostat as specified on
drawing
h. Check and record all voltage readings
i. Energize MSP one at a time to ensure correct motor rotation.
j. Ensure that CFM monitoring system is functioning (if applicable).