PN 76.8820IM30-A
Tellabs 8820 Multi-service Switch Router System Installation
1-2
Installation Overview
Overall Installation Sequence
Overall Installation Sequence
This section provides a quick-view of the 8820 MSR installation process.
1. Unpack and Inspect the 8820 MSR and Components
See
Unpacking the 8820 MSR, on page 2-2
for detailed instructions.
2. Prepare Power Source
Power feed cabling must be prepared to enable connection to the 8820 MSR DC block, and
the earth ground must be prepared for connection to the rear of the 8820 MSR. See
for details.
3. Position, and Cable the 8820 MSR
Prior to installing the 8820 MSR in a rack you may need to install the mounting brackets
provided with the equipment.
Step 1
Install the 8820 MSR, on page 4-3
Step 2
Step 3
Load the Chassis (Optional), on page 4-11
Step 4
Install Blank Panels, on page 4-13
4. Initialize the 8820 MSR
Use guidelines in the following sections for attaching the 8820 MSR to a network and
performing an initialization sequence.
❑
Connect the Local Console to the 8820 MSR, on page 4-15
❑
Connect the Ethernet (IP Management) Port, on page 4-20
❑
Apply and Verify Power, on page 4-16
❑
N
OTE
If you need to troubleshoot the bootup, refer to guidelines provided in