3.3.8 Installing Cable Management System (CMS)
Install the Cable Management System (CMS) as instructed by the manufacturer. If desired, use the large (17.5
mm diameter) holes at the top of the ADFs to connect the CMS to the lineup.
Telect, Inc. • USA +1.509.926.6000 • 52.33.3836.37.52
www.telect.com • © 2010 Telect, Inc., All Rights Reserved, 119736-4
Page 3-36
3.3.8 Installing Cable Management System (CMS)
Install the Cable Management System (CMS) as instructed by the manufacturer. If desired, use
the large (17.5 mm diameter) holes at the top of the ADFs to connect the CMS to the lineup.
Figure 34 - Connect CMS to Main ADF XIs
3.3.9 Grounding ADF
The bracket at the top of the Main ADFs contains two tapped holes to mount an approved dual-
hole lug with a #6 AWG (4.75 mm) grounding wire or strap. Refer to Figure 34.
Telect recommends using one ground wire or strap per Main ADF. Grounding wires or straps are
not provided with the ADF.
3.3.10 Securing ADF Lineup
After all ADFs of a lineup are installed, torque their tie-plate bolts to 80 N•m.
3.3.11 Wiring Facility Power
Facility power (AC) can be run into and through the electrical raceway at the foot of ADF XI and
IC lineups.
Figure 34 - Connect CMS to Main ADF XIs
3.3.9 Grounding ADF
The bracket at the top of the Main ADFs contain two tapped holes to mount an approved dual-hole lug with a
#6 AWG (4.75 mm) grounding wire or strap. Refer to Figure 34.
Telect recommends using one ground wire or strap per Main ADF. Grounding wires or straps are not provided
with the ADF.
3.3.10 Securing ADF Lineup
After all ADFs of a lineup are installed, torque their tie-plate bolts to 80 N•m.
3.3.11 Wiring Facility Power
Facility power (AC) can be run into and through the electrical raceway at the foot of ADF XI and IC lineups.