![TBEA TC500K3US-O Installation Manual Download Page 18](http://html1.mh-extra.com/html/tbea/tc500k3us-o/tc500k3us-o_installation-manual_823554018.webp)
TC500K3US-O Installation Instructions
12
2.2.3 Requirements Prior to Connecting the Switches on AC and
DC Sides
Breakers on AC, DC sides shall be disconnected and the protective panel
against accidental touch shall be installed or protective measures be taken.
All connections must be carried out in accordance with the installation
manual and schematics.
Protective earthing connection has been done with power grid
transmission and internal power supply.
Confirm that the inverter has been closed and locked.
Emergency stop switch is in loose status.
It shall be confirmed that the rated voltage, frequency and phase sequence
of the connection terminals on AC side are in line with requirements.
It shall be confirmed that the voltage polarity on DC side is correctly
connected.
Check PV array by insulation test to ensure no ground fault.