March 10, 2014
8
922-126-3 (3’) TRIPLE RAIL SLIDE
INSTALLATION INSTRUCTION
INSTALLATION STEPS CONTINUED
__9.
Insert the 3/8 x 3/8 socket set screws
(#10) into the threaded
hole on the bottom side of the four-hole attachment brackets (#4)
and tighten (Detail C on page 7).
__10.
Level and square the slide
making sure to keep 11” of
spacing from the slide bed to the top of the safety surfacing.
__11. Once slide is in position and you have verified its square and
level you may
tighten the bolts connecting the slide to the deck.
__12.
Inspect the components
for sharp edges and if necessary file
them down and apply touch up paint.
__13. Once the entire playground has been installed and you have
verified that the entire playground is level you can
add the
concrete to the footing holes.
Be sure to use concrete with a
minimum 2,500 psi and mix the concrete per the manufacturer’s
directions before you pour it into the footing hole. Once the footing
has been filled with concrete you should rope of the area for a
minimum of 48 hours to allow the concrete set properly.
__14.
Once the concrete has set,
back fill dirt over the footing
holes: inspect the area and components for tools, hazardous debris
and sharp edges. Verify all components are installed and all
hardware is tight and then install the safety surfacing.
__15.
Install labeling
as instructed in the appendix of the
instruction manual.
INSTALLATION STEPS CONTINUED
TIP: It’s easier to install the self tapping screws if you pre drill
the holes in the post with a #7 drill bit by marking the hole
locations with a dry erase marker after you have put the guard
wall into position.
Summary of Contents for QUICK SHIP 1 MODIFIED
Page 1: ...012 3 4 5 2 67 8 9 8 0 5 4 6 72 2ABCDB EBCF GHB BIGJEB KCILCA MBNOEB MBPJIIJIP JIDGCAACGJOI...
Page 2: ......
Page 4: ......
Page 6: ......
Page 7: ...QUICK SHIP 1 MODIFIED Installation Guide...
Page 8: ......
Page 10: ......
Page 12: ......
Page 14: ......
Page 28: ......
Page 30: ......
Page 32: ......
Page 35: ...March 10 2014 3 912 242 SQUARE DECK 46 INSTALLATION INSTRUCTION...
Page 42: ...March 10 2014 4 922 126 3 3 TRIPLE RAIL SLIDE INSTALLATION INSTRUCTION...
Page 50: ...March 11 2014 4 922 120 3 CORKSCREW 3 DECK INSTALLATION INSTRUCTION...
Page 64: ...September 17 2014 4 912 807 SAND WATER PANEL INSTALLATION INSTRUCTION...
Page 81: ...VALUE SERIES INSTALLATION APPENDIX 4 2 10 M C_APPENDIX V1 0410 1 INSTALLATION APPENDIX...
Page 82: ......
Page 88: ......
Page 112: ......