Carrying out welding
Step 5:
Check the lift height / drop time of the stud welding gun (see chapter
“11.1.5 Setting the lift height (drop time) in the "Setup" mode “ on page
67.
Step 6:
Check the inert gas supply and purge the gas line
(see chapter “11.1.4
Setting the gas preflow time (gas test)
Step 7:
Make sure the device is in the
operating mode by selecting one of
the upper three functions.
Step 8:
Check that the welding points on the stud and workpiece are metallically
bright.
Step 9:
Press the gun onto the workpiece at an angle of 90 degrees.
The LEDs light up red when the contact to the workpiece and earth
connection are correct.
Step 10:
Press the release button of the gun.
Welding is carried out. The LEDs
also briefly light up red during the
welding process.
During the welding process, hold the gun still and only remove it
vertically from the welded stud after completing the welding
process. By doing so, widening or damaging the stud chuck is
avoided.
The welding process is finished.