Switching on MyReserve Command
1. Start the inverter using the manufacturers starting
procedures.
2.
Close the DC isolator switch of the inverter.
3. Turn the DC isolator of MyReserve Command to the
ON position.
4. Check if PV voltage is applied to the inverter (associ-
ated MPP tracker).
5. Wait until the inverter has found its operating point.
6.
Switch on the AC power supply of the MyReserve
Command (green POWER toggle at the MyReserve
Command 25 bottom plate).
NOTE
On initial commissioning, a charge or discharge of the MyReserve only occurs if the electric current on con-
nected PV string is >0.3A and the installation location for the RfG country assignment is set.
Neither charging nor discharging occurs if these conditions are not met and MyReserve will remain in stand-
by mode.
NOTE
NOTE
NOTE
Checking Connection of Battery Modules
After switching on the MyReserve a test routine is con-
ducted to check the connection of the battery modules.
The results are indicated over the LED display of the My-
Reserve Command:
When the system is started, the status LED is initially
green for 5 seconds .
If the status LED continues to show green after more than
5s, turn OFF the MyReserve and check the connectors for
proper connection. To repeat the Test routine then restart
the MyReserve Command.