Sunny Island
Installation & Operating Instructions
BWRI33-12:EE
- 32 -
SMA Regelsysteme GmbH
Sunny Island
13
14
13
14
N
L
F2
G
L
N
external distribution
Generator
Diesel
start
Diesel
contactor
K1
K2
Generator
start
AC-
Outlet
2 A
L
N
PE
L
N
SI-
BPRE
SI-
BPRE
Fig. 3.10: Connection of a (diesel) generator
Three common options to start diesel generators are described in chapter 16.
In most switch-over situations the period of time for „short interruptions“ can be sub-
stantially reduced by means of a slightly more complicated cabling (Fig. 3.11). Natu-
rally, this time cannot be reduced in case of a shutdown of the generator – unpre-
dictable for the Sunny Island - (manual deactivation, failure due to fuel deficiency, or
the similar).