7SG164 Ohmega 400 Series Commissioning
©2011 Siemens Protection Devices Limited
Chapter 9 Page 6 of 6
operations occur correctly. If possible, using a P.C. or laptop computer loaded with Reydisp Evolution software,
check the current and voltage waveforms and relay operations. For phase-earth faults, check that correct
tripping as per scheme is obtained i.e. either single pole tripping or three pole tripping with the associated control
operations.
6 Putting Into Service
•
Remove the external test connections and heavy duty test plugs
•
Check that the current and voltage transformer are wired for normal operation
•
Check that all a.c. and d.c. supply links and fuses are inserted
•
Check that the earth links are inserted
•
Check that all the relay settings are as recommended.
•
Test and reset the LED indication display
•
Replace the relay cover
•
Insert the trip link