DA
L
19
65
Page13/18
PROGRAMMING THE CONTROL UNIT
The programming must be carried out point by point. In the case of errors during this phase, it is necessary to
proceed with new programming, which will delete the first.
Switch the control unit on and off to exit incorrect programming.
Before programming, the system must be complete with all electrical devices and safety devices connected
(buttons, photocells, flashing lights etc.).
Check their correct functioning:
In the case of anomalies check and remove the cause.
:
All signal LEDs of the NC inputs (stop, photocells, etc) are
on
.
All signal LEDs of the NO inputs (start, pedestrian) are
off
.
ATTENTION
The normally closed (NC) inputs that are not used must be jumpered.
PROGRAMMING WORK TIMES AND SLOWING FOR GATE WITH TWO LEAVES (DIP1 SW1 OFF)
With the control unit powered and the gate closes, press key A once (SET) to enter programming. The DL10
LED starts to flash to indicate that the control unit is in the programming state.
Wait for a period of time equal to the phasing that is to be given to motor M2 in the opening phase (max 15s),
now press the B (BREAK) key once to start the opening phase of motor M2 (after 15s it is started automatically).
While both leaves are opening, regulate the power of the motors by intervening on the POWER potentiometer.
ATTENTION: - If the POWER potentiometer is regulated too low, the gate cannot open. We
recommend that the POWER is regulated starting from MAXIMUM and gradually
dropping to minimum.
- The large temperature differences between the summer and winter cause
different dilation of materials, including those with which the motors are built.
For this reason it is recommended to control the regulation of the motor thrust
at the start of the winter and the summer.
ATTENTION: - If one or more parameters are varied, programming must be repeated from
the beginning.
- In the programming procedure, slowing has only been set in the closure
phase, but in normal functioning mode it is also introduced in the opening
phase.
Press key C (WORK) once to start the opening phase of motor M1 (M2 remains at a standstill).
When the leaf connected to M1 is against the opening stop, wait a few seconds (3-4s max) and then press key
C (WORK) once. The motor M1 is switched off.
When the leaf connected to M2 is against the opening stop, wait a few seconds (3-4s max) and then press key
B (BREAK) once. The motor M2 is switched off.
When the leaves are completely open and the motors are powered, press key B (BREAK) once to start the
closing phase of the motor M2 (M1 remains at a standstill).
Wait for a period of time equal to the phasing that is to be given to motor M1 in the closing phase (max 15s),
now press the C (WORK) key once to start the closing phase of motor M1 (after 15s it is started automatically).
When Motor M2 should start flowing (we recommend at least 50cm before the stop) press key B (BREAK). The
motor M2 slows down.
ATTENTION: jump this point id slowing has been excluded (DIP2 SW2 ON)
When Motor M1 should start slowing (we recommend at least 50cm before the stop) press key C (WORK). The
motor M1 slows down.
ATTENTION: jump this point id slowing has been excluded (DIP2 SW2 ON)
When the leaf connected to M2 is against the closing stop, wait at least 5 seconds and then press key B
(BREAK) once. The motor M2 is switched off.
When the leaf connected to M1 is against the closing stop, wait at least 5 seconds and then press key C
(WORK) once. The motor M1 is switched off and the control unit exits automatically from the programming
phase and is ready for normal functioning.
K
IT
/A
9
I
E