The generator will also start if there is a persistent load on the batteries.
Battery Load sets the level at which the generator will be started if the
average load exceeds the preset level for more than 5 minutes.
Battery Load is the actual current being drawn from the battery bank. For
example, if say solar is providing all the power to the site load, then no
current will be coming from the battery bank i.e. Battery Load is 0kW and
the generator won’t be started.
On 15min Load is similar to the previous screen except the settings
take effect if the average load exceeds the preset limit for more than 15
minutes.
We previously discussed mid point monitoring and its ability to help
determine a battery fault. This screen allows you to choose if a mid point
Voltage Error should start the generator.