On the network play setting screen, set LINK NUM. Press the SERVICE Button, move the cursor onto
LINK NUM and select it.
When the TEST Button is pressed, the LINK NUM preset value changes. Set “2” in each of the two game
machines. When “2” has been set, LINK ID appears below LINK NUM.
FIG. 20-3b
Press the SERVICE Button, move the cursor to LINK ID and select it.
When the TEST Button is pressed, the preset value of LINK ID changes. Set [1] in one machine and [2] in
the other machine.
Press the SERVICE Button and move the cursor to EXIT.
10
When the TEST Button is pressed, the network play setting screen exits and the game test mode menu
reappears.
11
Press the SERVICE Button, move the cursor to EXIT and press the TEST Button. The system test mode
menu reappears.
1
Press the SERVICE Button, move the cursor to EXIT and press the TEST Button. The test mode terminates.
Note that initialization now takes place when the power is engaged.
1
Upon completion of initialization, network check begins. The monitor screen shows that network check is in
progress.
1
If there are no problems with the connections and settings for network play, the Attract Mode is established.
When the Attract Mode screen appears, setting is completed.
Network check will be completed after about 20 seconds or longer. If the network check screen continues to
be displayed, there could be an error in the settings, error in the network cable connections, faulty network
cable connection, cable disconnection, etc.
Summary of Contents for AFTER BURNER CLIMAX
Page 12: ...1 HANDLING PRECAUTIONS FIG 1b FIG 1c FIG 1d...
Page 50: ...7 PRECAUTIONS WHEN MOVING THE MACHINE 42 FIG 7 1b...
Page 58: ...8 GAME DESCRIPTION 50 FIG 8b FIG 8c...
Page 80: ...EXPLANATION OF TEST AND DATA DISPLAY FIG 9 3a03...
Page 83: ...EXPLANATION OF TEST AND DATA DISPLAY 9 75 FIG 9 3b03...
Page 151: ...TROUBLESHOOTING 17 143 3 Remove the front door FIG 17 3b 4 Replace fuse inside base FIG 17 3c...
Page 176: ...22 PARTS LIST 168 PARTS LIST 22...
Page 181: ...PARTS LIST 22 173 2 ASSY ROLLING BASE ABX 1000 D 1 3 Fastening Torque...
Page 190: ...22 PARTS LIST 182 8 MOTOR UNIT ABX 3200 D 1 2 Fastening Torque...
Page 205: ...PARTS LIST 22 197 22 ASSY MONITOR BOX ABX 1100 D 1 2 Opposite side...
Page 209: ...PARTS LIST 22 201 25 ASSY COINCHUTE TOWER ABX 1200 D 1 2 Coin Box Part...
Page 216: ......
Page 217: ...PARTS LIST 22 209 32 ASSY BILLBOARD ABX 1500 D 1 2...
Page 223: ...PARTS LIST 22 215 36 THROTTLE UNIT ABX W O GRIP 610 0758 D 1 2...
Page 225: ...PARTS LIST 22 217 37 ASSY SEAT UPPER ABX 1700 D 1 2...
Page 233: ...225 WIRING DIAGRAM 24 WIRING DIAGRAM D 1 2 24...
Page 234: ...226 WIRING DIAGRAM 24 D 2 2...