Page 12
OMEGA IPL Installation Guide
Part No. 000823, 06-m02-2012
b. Assemble the two metal half rings (5) and the two
plastic parts (4) shown below onto the tension rope
and then slide the rope lever over these parts
(shown below).
Figure 24
Plastic part into rope lever
c. Install the plastic cover (8) over the plastic part,
metal half rings and rope lever that you just
assembled (see below).
Figure 25
Install plastic cover over plastic part and metal half rings
d. Draw back the tension rope (1) from the top of the
railway, while at the bottom of the railway inserting
the rope lever (6) into the slot on the lower side of
the upper tube (see below).
Figure 26
Rope lever into upper tube
e. Assemble the sliding contact (3) parts – plastic part,
four springs, and two contacts (shown below). Note
that you will need to hold the parts in place to slide
the whole assembly into the tube.
Figure 27
Assemble sliding contact
f. Slide the contact assembly (3) into the upper tube
next to the tension (upper) rope lever (6). See the
next two photos.
Figure 28
Slide contact assembly into upper tube