Page 28
OMEGA IPL Installation Guide
Part No. 000823, 06-m02-2012
Step 20
Check the installation
Check the installation before using the lift.
Procedure
1
Refer to the Electrical Schematics shipped with the lift
and verify all electrical connections.
2
Ensure that the electrical equipment and wiring comply
with the applicable codes.
3
Verify that all microswitches are positioned correctly.
4
Verify that all mechanical components are installed per
the instructions in this guide and that all hardware is
tightened.
5
Verify that all rail and post hardware is present and
firmly tightened.
6
Verify that all other hardware is present and tightened.
Step 21
Test operation
Test the operation of the stairlift.
Procedure
1
Unfold the platform and run the lift up and down the
stairs. Check all travel clearances.
2
Verify that the red warning lamp on the platform
control panel is illuminated when the unit is running.
3
Verify that all pendant and call station controls are
functioning properly.
4
Verify that the platform folds and unfolds properly.
5
Verify that the loading ramps open and close at the
landing stop positions.
6
Verify that the lift stops when it contacts an obstacle
along the travel route.
7
Check the operation of the limit switches. The upper
and lower limit switches should stop the lift when it
reaches the top or bottom of the stairway.
8
Reinstall any covers that were removed during
installation.