OPTIMAX - INSTALLATION INSTRUCTIONS
ROXELL - 004 - 2414
III- 12
SUSPENSION FOR FEEDER LINE
SUSPEND THE CONTROL UNIT AT LEAST 3M FROM THE HOUSE END WALL !
PROCEDURE :
- First determine the position of the feeder lines.
- Then measure the distance from the wall to the first feeder line.
- Mark from this spot the suspension points on the ceiling over the whole length of the line.
Alternatives : see page 24.
Fix the suspension points
(well aligned !)
every 2,4m. Hook
openings point away from the central winch.
FIGURE 26.
CENTRAL WINCH
Wooden beam.
Beam
Suspension cord
Main cable 5mm
Screw hook with pulley.
If H more
than 2,4m.
(L = 3M)
FIGURE 27.
H
If winching-up height (H) exceeds 2,4m, place suspension hooks crosswise off the beam center line. So the
cable clamps will not touch the pulleys when you wind up the line.
(Max. 3,5M)
If lifting height is more than 2,4m, you can install the central winch somewhat out of line. So the pulleys will
not touch the cable clamps. (Alternative system : see Fig. 34.)
FIGURE 28.
You will not get any differences in level along the line as long as you respect
the distances at the first two cable attachments.
Cable
Feeder line.
25cm
15cm
25cm
25cm
25cm
15cm
15cm
15cm
0cm
0cm
Summary of Contents for Optimax
Page 8: ......
Page 9: ...I 1 PART I INSTRUCTIONS FOR THE USER ...
Page 10: ...OPTIMAX INSTRUCTIONS FOR THE USER ROXELL 004 2111 I 2 ...
Page 24: ...ROXELL 004 2414 OPTIMAX COMPONENTS II 2 GENERAL LAY OUT ...
Page 53: ...III 1 PART III INSTALLATION INSTRUCTIONS ...
Page 54: ...OPTIMAX INSTALLATION INSTRUCTIONS ROXELL 004 3503 III 2 NOTES ...
Page 56: ...OPTIMAX INSTALLATION INSTRUCTIONS ROXELL 004 2414 III 2 GENERAL LAY OUT ...
Page 91: ......