Checklist after start-up
A
Is the system working without any faults (noise emission, operation, fault codes)?
Yes
B
Does the system become hot in heating operation and cold in cooling operation
1)
?
Yes
C
Is the system water pressure within the specified range?
Yes
D
Are the components connected as an option working faultlessly with the ROTEX HeatPumpSolarUnit?
Yes
E
Has the configuration of the ROTEX HeatPumpSolarUnit been checked and adapted to the operating conditions and the user
parameters?
Yes
F
Has the automatic test run been carried out successfully?
Yes
G
Has the evacuation function been tested?
Yes
H
Has the operator been informed of the documentation obligation concerning annual maintenance and certification of refrigerant fill
quantities in accordance with F-Gas Directive (EU) No. 842/2006?
Yes
I
In the case of new installations: Have the operating instructions and operating manual been handed over and has the operator been
trained?
Yes
1)
The function room cooling is available only for systems of type "HPSU..X".
Only if
all points
on the check list can be answered with
Yes
may the ROTEX HeatPumpSolarUnit be handed over to the operator.
Location and D
ate:
Signature of installer:
Signature of owner: