8.3 Stow Test Circuit #3 (Stowed State)
Step
Procedure
Date & Initials
Tech.
QA
8.3.1
Set up the
Test Circuit: Stowed
portion of
Stow Test Circuit #3
per Figure 8-3
and connect to the
Stow Power and Measurement Circuit
.
Figure 8-3: Stow test circuit #3