Notes on safety for the maintenance
The periodic maintenance is essential for the good operation,
safety, yield and duration of the burner.
It allows you to reduce consumption and polluting emissions and
to keep the product in a reliable state over time.
Before carrying out any maintenance, cleaning or checking oper-
ations:
9.2
Maintenance programme
9.2.1
Maintenance frequency
9.2.2
Safety test - with gas feeding closed
For its safe commissioning it is very important to make sure that
the electrical wiring has been carried out correctly between the
gas valves and the burner.
To this end, after checking that the connections have been made
in conformity with the burner's wiring diagram, a starting cycle
should be carried out with the gas tap closed (dry test).
1
The manual gas valve should be closed with the locking/re-
leasing device (“lock-out / tag out” procedure).
2
Make sure the limit electric contacts of the burner close
3
Make sure the contact of the minimum gas pressure switch
closes
4
Proceed with a tentative start up of the burner.
The starting cycle should occur with the following phases:
–
Starting the fan motor for pre-purging
–
Carrying out the gas valve leak detection control, if applicable
–
Completing the pre-purging
–
Reaching the ignition point
–
Power supply of the ignition transformer
–
Power supply the gas valves.
Since the gas is closed, the burner will not be able to start and its
control box will stop or go into a safety lockout.
The effective supplying of the gas valves can be checked with the
insertion of a tester; some valves are fitted with light signals (or
closure/opening position indicators) that are activated when the
electrical supply arrives.
9.2.3
Checking and cleaning
Combustion head
Open the burner and make sure that all components of the combus-
tion head are in good condition, not deformed by the high tempera-
tures, free of impurities from the surroundings and correctly positioned.
Burner
Check that there are not excess wear or loosen screws.
Clean the outside of the burner.
Fan
Check to make sure that no dust has accumulated inside the fan
or on its blades, as this condition will cause a reduction in the air
flow rate and provoke polluting combustion.
Boiler
Clean the boiler as indicated in its accompanying instructions in
order to maintain all the original combustion characteristics in-
tact, especially the flue gas temperature and combustion cham-
ber pressure.
Gas leaks
Make sure that there are no gas leaks on the pipe between the
gas meter and the burner.
9
Maintenance
DANGER
The maintenance interventions and the calibration
of the burner must only be carried out by qualified,
authorised personnel, in accordance with the con-
tents of this manual and in compliance with the
standards and regulations of current laws.
DANGER
Disconnect the electrical supply from the burner
by means of the main system switch.
DANGER
Turn off the fuel interception tap.
Wait for the components in contact with heat
sources to cool down completely.
The gas combustion system should be checked at
least once a year by a representative of the man-
ufacturer or another specialised technician.
WARNING
IF THE ELECTRICAL SUPPLY OF THE GAS
VALVES OCCURS AT AN UNEXPECTED MO-
MENT, DO NOT OPEN THE MANUAL VALVE,
DISCONNECT THE ELECTRICAL SUPPLY,
CHECK THE WIRING; CORRECT THE ER-
RORS AND CARRY OUT THE ENTIRE TEST
AGAIN.
The operator must use the required equipment
during maintenance.
Summary of Contents for 20155654
Page 2: ...Original instructions...
Page 73: ...71 20155699 GB Appendix Electrical panel layout RS 310 410 E FGR...
Page 74: ...20155699 72 GB Appendix Electrical panel layout RS 510 610 E FGR...
Page 75: ...73 20155699 GB Appendix Electrical panel layout 01 2 3 4506 7 891 01...
Page 76: ...20155699 74 GB Appendix Electrical panel layout...
Page 77: ...75 20155699 GB Appendix Electrical panel layout 0 0 0 1 1 1 2 1 3 1 1 1 1 1 1 1 41 4 4 1 1 2 1...
Page 78: ...20155699 76 GB Appendix Electrical panel layout 0 0 0 1 1 23 4567 23 4567...