20155699
54
GB
Options
8.1.10 Control mode
The firing rate controller is attempting to adjust actual value to
set-point value.
A direct correlation is assumed between internal firing rate and
boiler temperature, i.e. the higher the internal firing rate, the fast-
er boiler the rise of temperature.
If curves are programmed in a different way the firing rate control-
ler will not operate. Four parameters define the control character-
istics:
•
Adjustment time
Adjustment time defines the intervals of deviation is checked
and a new adjustment is determined.
•
P term
The proportional term affects directly on deviation defined as
difference between set-point value and actual value.
P >
higher step response
•
I term
The integral term is calculated from present deviation and
previous deviation to set-point value
I >
faster approximation to set-point
danger of over-
shooting!
•
D term
The difference term is calculated from variation of actual val-
ues. This may result in accelerating, respectively retarding ef-
fects.
In practice adjustments of PID-controller is orientated by given
controlled system. Out of characteristics of the controlled system
data can be deduced, i.e. by experimental determination.
–
P share, I share, D share are added up and serve as adjust-
ments to the firing rate default of the fuel/air ratio control.
–
As long as the actual value is below set-point, P term and I
term are positive, that is to say both of these terms will in-
crease the firing rate default.
–
In such a case only D term has a negative value (assuming
that boiler temperature is rising). Use D term carefully be-
cause it leads to a higher burden for the actuating elements.
–
In order to avoid excessive overshoot during burner start-up
adjust parameters to achieve a suitably large D term.
–
If despite a large set-point deviation the burner is not run at
full or base firing rate you should increase the P term.
–
The longer you select the adjustment time the calmer the fuel/
air ratio control. However, this also increases the actual val-
ues’ deviation from set-point value and leads to slower ad-
justment.
Tab. N
Adjustment of the values according to the controlled system is
highly recommended.
Hot water
installations
Steam boiler
installations
P term
120
280
600
I term
60
360
300
D term
20
50
25
Adjustment
time
15
2
20
Summary of Contents for 20155654
Page 2: ...Original instructions...
Page 73: ...71 20155699 GB Appendix Electrical panel layout RS 310 410 E FGR...
Page 74: ...20155699 72 GB Appendix Electrical panel layout RS 510 610 E FGR...
Page 75: ...73 20155699 GB Appendix Electrical panel layout 01 2 3 4506 7 891 01...
Page 76: ...20155699 74 GB Appendix Electrical panel layout...
Page 77: ...75 20155699 GB Appendix Electrical panel layout 0 0 0 1 1 1 2 1 3 1 1 1 1 1 1 1 41 4 4 1 1 2 1...
Page 78: ...20155699 76 GB Appendix Electrical panel layout 0 0 0 1 1 23 4567 23 4567...