7.6
Starting and stopping the boiler
7.6.1
Commissioning
Caution
Initial commissioning must be done by a qualified professional.
If adapting to another type of gas, e.g. propane, the boiler must
be adjusted before it is switched on.
1. Open the main gas valve.
2. Switch the power on with the boiler's on/off switch.
The boiler starts before the control panel display is active.
3. Set the following parameters when the appliance is first switched on:
Select Country and Language
Configure the date and time used by the appliance
Enable Daylight Saving Time
CN1 and CN2 (codes present on the boiler data plate).
4. Set the components (thermostats, control system) so that they request
heat.
5. Check the hydraulic pressure in the installation shown on the control
panel display.
Recommended hydraulic pressure between 0.15 and 0.2 MPa (1.5
and 2.0 bar).
Important
In the event of an error during start-up, a message with the
corresponding code is displayed. The meaning of the error codes
can be found in the error table.
7.6.2
Shutting down the boiler
The boiler must be shut down in order for certain operations to be carried
out on the equipment or its environment.
In other situations, such as an extended absence period we recommend
that Holiday Mode mode is used in order to benefit from the heating pump
anti-blocking function and to protect the installation from frost.
To shut down the boiler:
1. Press the on/off switch.
7.7
Gas settings
7.7.1
Adapting/adjusting the boiler to different types of gas
1 Gas valve unit on the
Gas 120 ACE - 65
Gas 120 ACE - 90
2 Gas valve unit on the
Gas 120 ACE - 115
Warning
Only a qualified engineer may carry out the following operations.
The boiler is pre-set in the factory to run on G20 type natural gas (H gas).
Before operating with a different type of gas, carry out the following steps:
Fig.46
AD-0000067-02
A
A
1
2
7 Commissioning
34
MID _HMI T-control - Gas 120 ACE
7717201 - v03 - 25062019