9. Check the tightness of the flue gases evacuation and air inlet
connections.
10.Checking the hydraulic pressure. If necessary, top up the water
level in the heating system (recommended hydraulic pressure
between 1,5 and 2 bar).
11.Tick the gas category used on the data plate.
12.Complete the checklist in the supplied service book.
13.Explain the operation of the installation, the boiler and the
regulator to the users.
14.Give all the instruction manuals to the user.
15.Together with the end user, fill in the warranty sheet provided.
16.Confirm the commissioning with a signature and a company
stamp.
5.6
Reading out measured values
5.6.1.
Reading the various current values
The following current values can be read off the information menu
Q
:
4
5t
= State.
4
5v
= Sub-status.
4
t1
= Supply temperature (°C).
4
t"
= Return temperature (°C).
4
t3
= Calorifier temperature (°C).
4
t4
= Outside temperature (°C) (Only with an outside
temperature sensor).
4
t5
= Solar boiler temperature (°C).
4
5p
= Internal set point (°C).
4
fl
= Ionization current (µA).
4
Mf
= Fan speed in rpm.
4
pr
= Water pressure (bar).
4
p;
= Supplied relative heat output (%).
Calenta 25s - 28c - 35s - 40c
5. Commissioning
040412 - 7600585-01
61