The correct operation of this equipment depends on the instructions in this
manual. To secure the equipment, proceed as follows:
Step 1:
Make sure the floor
is firm enough so that the
equipment can be screwed on
a level. If it does not comply
with the requirement, provide
a concrete base, following the
guidelines in the right image:
Step 2:
The dimensions of the base should be appropriate for the dimensions of
the operator. The concrete base should be at a distance of approximately 25 mm
from the face of the gate leaf.
GATE LEAF
SIDE VIEW
CONCRETE BASE
Step 3:
When the conditions are fulfilled, open the gate and position the operator
near the face of the gate leaf, obeying the 50 mm measurement between the leaf
end and the operator.
GATE LEAF
Step 4:
Pre-align the operator with the gate, positioning the rack over the gear
and pushing the assembly to the gate. Then mark the fixing holes in the floor or
concrete base.
MARK THE FIXING HOLES
ON THE FLOOR
Step 5:
Drill the holes for fastening. Place the operator aligned to the gate and
insert the 3/8” x 3.3/4” bolts without tightening them. Move the gate, making sure
that it does not lean against the operation during the during its travel. If this occurs,
pull back the operator.