Pushbutton Connection “PBU”

The board recognizes a button control when the PBU terminal is connected to 

the GND, ie a pulse for GND.

Terminal 1: GND (-);
Terminal 4: PBU (Normally Open Contact - N.O.).

Pushbutton Connection for only opening “OPE”

The board recognizes an opening command when the OPE terminal is 

connected to the GND, ie a pulse for GND.

Terminal 1: GND (-);
Terminal 5: OPE (Normally Open Contact - N.O.).

Pushbutton Connection only for closing "CLO"

The board acknowledges a closing command when the CLO terminal is 

connected to the GND and then released, ie a pulse for GND and then the button 

must be released.

This can also be used in access control systems that use photocells or inductive 

loops to automatically close the gate or barrier.

Terminal 1: GND (-);

  Terminal 6: CLO (Normally Open Contact - N.O.).

ATENTION

:

 The Control Board provides 15 V (maximum 

continuous current of 120 mA) for powering photocells and 

receivers AND DOES NOT HAVE OVERCURRENT PROTECTION. 

If the external optional equipments require more voltage or 

current, it will be necessary to use an auxiliary power supply

.

Connection of reed sensors limit switch “MGS”

  The control board acknowledges an activated ‘reed’ when the pin corresponding 

to it on the MGS pin bar is connected to the GND, i.e., a pulse to the GND.

The only condition that must be followed is that the reed that represents the open 

gate must be connected in such a way that the ‘MSO’ LED lights. And the ‘MSC’ LED 

must light when the gate is closed.

“PROG” Connection

External communication connector on control board for use with PROG or BLUE.

“UPS_C” Connection

This connector is the communication between the board and the PPA Nobreaks. 

With this connection installed, the board optimizes operation when it is operating 

without power from the mains, ie by the batteries.

What is optimized:

1 - The board reduces the power consumption when the engine is switched on 

by reducing the work speed, saving up to 50% on battery;

2 - When the control board is in standby, with the gate open or closed, the 

motor is off. The control board then sends a command to the PPA Nobreak to turn 

off the power control stage and reduce the battery consumption, increasing the 

autonomy. With this feature, main power may be disconnected for several hours 

without completely draining the battery. Only the RF receiver and the controls 

are energized directly by the battery, which allows the control board to receive a 

command and only after that the PPA Nobreak reconnects the power control stage 

and the operator starts the movement. This system is patented by PPA.

Summary of Contents for DZ 2.0

Page 1: ...hado 3526 Distrito Industrial CEP 17400 000 Gar a SP Brasil www ppa com br 55 14 3407 1000 callcenter ppa com br WARNING Do not use the product without first reading the instruction manual Technical M...

Page 2: ...pe AUTOMATIC GATE OPERATOR FOR SLIDING GATES Models DZ IND 2 0 DZ IND 1 5 DZ IND 1 0 DZ RIO 800 DZ RIO 500 The object of the declaration described above is in conformity with the following essential r...

Page 3: ...d in accordance with BS EN 12445 Test method using an appropriate tool Protective devices installed must comply with EN 12978 Safety devices Check the automation periodically with special attention to...

Page 4: ...disconnect device and the operator supply terminals the control board and the optional external pushbutton the control board and the photocells The wires used must comply with the local standards The...

Page 5: ...ns of the gate shall be in perfect running condition and shall be mounted in such a way that the gate leaf has stability along all its displacement We recommend pulleys with a diameter of at least 120...

Page 6: ...ate leaf GATE LEAF SIDE VIEW CONCRETE BASE Step 3 When the conditions are fulfilled open the gate and position the operator near the face of the gate leaf obeying the 50 mm measurement between the lea...

Page 7: ...ate leaf with solder or screw every 300 or 400 mm OR OR Step 8 If the gate leaf is warped provide shims to ensure alignment of the rack There are cases where the rack should pass the length of the gat...

Page 8: ...and place the other magnet holder on the rack facing forward with the operator REED This magnet will act as an opening limit switch MAGNET HOLDER REED SUPPORT Step 3 Remove the plastic covers to gain...

Page 9: ...the Transmitters recorded in encrypted form The board is also compatible with Rolling Code Transmitters with PPA s own protocol System activation can be carried out via remote control through the buil...

Page 10: ...E Before connecting the optional accessories Electromagnetic Lockand orGarageLight Signal pushbuttonsandetc itisadvisable to carry out a general test of machine operation To do this simply press the b...

Page 11: ...the pin corresponding to it on the MGS pin bar is connected to the GND i e a pulse to the GND The only condition that must be followed is that the reed that represents the open gate must be connected...

Page 12: ...ED flashes rapidly for short time interval and then indicates the parameter value The following table shows the number of blinks for each function Number of flashes Reference model 1 Lightweight Gate...

Page 13: ...can be closer or far from the stop The minimum value of 0 LED flashes increment and decrement from 1 to the maximum value of 10 LED lit Important To test the changes it is necessary to operate the gat...

Page 14: ...addition the PROG display informs you whether the traffic light function or the Pre flashing Time function is enabled SLS DIP 3 1 2 3 4 5 6 7 8 ON END OFTRAVEL SPEED Speed when the gate is next to a t...

Page 15: ...he factory settings are applied RECORD A RADIO FREQUENCY TRANSMITTER RF In order to record an RF transmitter slide the dip 1 of the DS1 dip switch to on position press the button of the transmitter to...

Page 16: ...decreases to less than 100 C EEPROM fault The OSC LED flashes twice when Memory is not present EEPROM with invalid data The OSC LED flashes three times when Memory is present but it has a content tha...

Page 17: ...switch connector analog and or digital C Defect in the commanc board C Replace the board The gate does not correspond to the path of the place where the operator has been installed it brakes before i...

Page 18: ...LOCKING PIN 20 1 P04410 MOTOR UPPER BASE 21 1 P04411 MOTOR UNDER BASE 22 1 P04412 MOTOR UPPER COVER 23 1 P04413 UNLOCKING HANDLE SET 23 1 2 C10896 M5 X 16MM TORX SCREW 23 2 1 C10963 STEEL LOCK 1 2 THR...

Page 19: ...G PIN 20 1 P03746 BRUSHLESS DC ROTOR SHAFT 21 1 P04410 MOTOR UPPER BASE 22 1 P04411 MOTOR UNDER BASE 23 1 P04412 MOTOR UPPER COVER 24 1 P04413 UNLOCKING HANDLE SET 24 1 2 C10896 M5 X 16MM TORX SCREW 2...

Page 20: ...UNLOCKING PIN 20 1 P04410 MOTOR UPPER BASE 21 1 P04411 MOTOR UNDER BASE 22 1 P04412 MOTOR UPPER COVER 23 1 P04413 UNLOCKING HANDLE SET 23 1 2 C10896 M5 X 16MM TORX SCREW 23 2 1 C10963 STEEL LOCK 1 2 T...

Reviews: