Operation . 45
To start a stored cycle
1.
Use the arrow buttons
and
to set the Lower display to
C-01
for cycle one or
C-02
for cycle two.
2.
Press FUNC to start the cycle.
The system is now in RUN status.
3.
Press FUNC repeatedly to step through the sequence of information: setpoint, cycle
time, current step.
To determine the performance of the setup, compare the setpoint (displayed in red)
with the actual temperature (displayed in green). The cycle time gives the total running
time and the current step is displayed as
S-01
, for example.
4.
The cycle can be modified whilst it is running. Use the arrow buttons to change the
setpoint, cycle time or current step value as it is shown in the Lower display.
5.
To end the cycle prematurely, hold FUNC for two seconds until the system ‘beeps’.
When the cycle has ended without intervention, the Lower display shows
END
and the
Upper display shows the current temperature.
NOTE:
It is important to always use limit alarms to avoid damage to the samples and/or the
cells. Undesired overheating or overcooling may occur if the alarms are not used.
Refer to parameters P-01 and P-02 in
Configuration Parameters on page 47.
Summary of Contents for PTP-1
Page 1: ...Peltier Temperature Programmer User s Guide...
Page 5: ...Introduction...
Page 10: ...10 Peltier Temperature Programmer User s Guide...
Page 11: ...Warnings and Safety Information...
Page 18: ...18 Peltier Temperature Programmer User s Guide...
Page 19: ...Installation...
Page 30: ...30 Peltier Temperature Programmer User s Guide...
Page 31: ...Description...
Page 36: ...36 Peltier Temperature Programmer User s Guide...
Page 37: ...Operation...
Page 47: ...Configuration and Maintenance...