15
g. Route the non-diffuser end of the long
hose through the hole in the tile floor.
h. Route the short hose (already attached to
Pressure Node) through hole in the cabinet
floor.
i.
Using gentle but firm pressure, attach the
long diffuser hose to the high-pressure inlet
(+) on the Pressure Node
.
2. Activate, position, and secure the Pressure Node.
a. Once hoses are connected, activate the Pressure
Node by inserting a thin blade screwdriver into the
recessed slot of the node and slide the switch to the
ON position
b. Ensure the Pressure Node is active. Light Emitting
Diodes (LEDs) on the Pressure Node will blink during
activation. Full activation sequence lasts from 10
minutes to over an hour depending on the network
environment.
c. Clean area where Pressure Node will reside with alcohol
wipes. Allow area to dry thoroughly.
d. Attach 3M Command Strips to the underside of the
Pressure Node (if not already present).
3. Finalize hose routing, replace tiling, and clean area.
PRESSURE NODE INSTALLATION MANUAL